80sqm units now availalbe for occupancy20 Oct 2010Units 13 &14 on the Lee Rd side of the site are now available for occupany. Up to one year's rent free may be offered to the right tenant. Terms and conditions apply. Contact us for details. |
|
Taradale Information Centre now open20 Oct 2010Taradale Information Centre opened in unit 12 September 2010. |
|
NOW LEASING - Stage 2 of The Busy Corner Redevelopment16 Mar 2010Street upgrade works timeline confirmed with works expected to be completed in November 2010. As a result, stage 2 of the Busy Corner re-development is underway with new tenants sought. |
|
Unit 12 - Now leased16 Mar 2010New Information and Business centre to open in May / June 2010 |
|
$3.5M Taradale Streetscape upgrade begins Mar 201001 Mar 2010Street-cape upgrade to be undertaken by Napier City Council commences in Lee Rd carpark March 2009. |
|
Gotcha Treats opens Dec 200907 Dec 2009Gotcha Treats opens at The Busy Corner December 2009 |
|
Refurbishment of units 12-16 commences at Busy Corner Dec 200901 Dec 2009Refurbishment of units 12-16 complete at Busy Corner Dec 2009 commences. Units 12-16 will be available for occupation at The Busy Corner from May 2010. |
|
Busy Corner redevelopment opens15 Mar 2009Busy Corner redevelopment opens with upmarket 4 Square Supermarket. Stage 2 online late 2009 |
|
Walkway upgrade completed by Beaton Group. Café / wine-bar opens15 Jan 2008Walkway upgrade completed by Beaton Group. Café opens |
|
Visage Hair opens15 Oct 2007Visage Hair opens |
|
$2.3M for Taradale upgrade in 2006/07 LTCCP15 Dec 2005$2.3M for Taradale upgrade in 2006/07 LTCCP |
|
Council and Beaton Group discussions06 Jul 2004discussions with Council and Beaton Group regarding New World development resulted in council undertaking wider Taradale Main Street Study. Stakeholder discussions commenced |
|
Timeline
Jul, 2004 Council and Beaton Group discussions
Dec, 2005 $2.3M for Taradale upgrade in 2006/07 LTCCP
Oct, 2007 Visage Hair opens
Feb, 2008 Walkway upgrade completed by Beaton Group. Café / wine-bar opens
2009 The Busy Corner refurbishment opens - STAGE 1
Dec, 2009 The Busy Corner refurbishment opens - STAGE 2
2010 $3.5M Gloucester St upgrade commences with completion Nov 2010